Due to serious electrical repair delays restored power is not expected to be back up until middle if the night. ITS staff will return onsite at 7am tomorrow to bring systems back online provided power is back up by then.
Power restored six hours after original deadline. Issues with data center cooling resolved around 12 am. Some core services restored through night by on-site staff.
Additional ITS staff now heading in from across Detroit to bring systems up.
Many services are now up however a few are still in the works. Your patience is most appreciated as we get everything in place as it needs to be for the start of the school year.
6 comments:
Power restored six hours after original deadline. Issues with data center cooling resolved around 12 am. Some core services restored through night by on-site staff.
Additional ITS staff now heading in from across Detroit to bring systems up.
Many services are now up however a few are still in the works. Your patience is most appreciated as we get everything in place as it needs to be for the start of the school year.
Athletics and blackberry users may be receiving email on their devices. Staff working to fix this soon. Access email from outlook for now.
That is may not be receiving
IMAP access from off campus to the exchange server is not working.
Staff looking into IMAP issue.